WSMSMISTI · GD-WAT

KPI & Performance

Manual / Bulk / API: ConditionalINT-106 KPI Retrieval API — consumption

Operator actual vs plan

Read-only — no value is stored in M11Reads the operational report values captured in Monitoring (M09); plan values are those the operator declared for the period

No operational report values captured in this session yet

Water-loss rate
—
(produced − sold) ÷ produced
Average production per day
— m³
produced ÷ production days
Average sales per connection per month
— m³
sold ÷ customers ÷ months
Average selling price
— riel/m³
water-sales revenue ÷ sold
Total revenue
— riel
Σ revenue categories

Actual, plan and variance — 2026-Q2

Actual, plan and variance — 2026-Q2
ItemUnitTypeActualPlanVarianceVariance %Plan rate
P-01Production capacitym³/dayINPUT—————
P-02Supplied waterm³/dayCALCULATED—————
P-03Supply durationhours/dayINPUT—————
P-04Production durationhours/dayINPUT—————
P-05Supply pressurebarINPUT—————
P-06At high-demand hoursmetreINPUT—————
P-07At low-demand hoursmetreINPUT—————
T-01Water producedm³INPUT—————
T-02Water soldm³INPUT—————
T-03Water-loss rate%CALCULATED—————
T-04Production daysdaysINPUT—————
T-05PAC quantitykgINPUT—————
T-06PAC unit useg/m³CALCULATED—————
T-07Alum quantitykgINPUT—————
T-08Alum unit useg/m³CALCULATED—————
T-09Lime quantitykgINPUT—————
T-10Lime unit useg/m³CALCULATED—————
T-11Chlorine quantitykgINPUT—————
T-12Chlorine unit useg/m³CALCULATED—————
T-13Electricity consumptionkWhINPUT—————
T-14Electricity unit useW/m³ (as printed)CALCULATED—————
T-15Diesel consumptionlitreINPUT—————
T-16Diesel unit usemL/m³CALCULATED—————
B-01House connections madeconnectionsINPUT—————
B-02Connection revenuerielINPUT—————
B-03Customers at end of periodcustomersINPUT—————
B-04Water use per connection per monthm³CALCULATED—————
B-07Average selling priceriel/m³CALCULATED—————
B-08Water-sales revenuerielINPUT—————
M-01Water meters readunitsINPUT—————
M-02Water meters repairedunitsINPUT—————
M-03Water meters replacedunitsINPUT—————
F-03Other revenuerielINPUT—————
F-04Total revenuerielCALCULATED—————
A-01Staff — grand totalpersonsCALCULATED—————
C-05Connections — totalconnectionsCALCULATED—————
N-01Total network lengthmCALCULATED—————
N-04New network extensionmCALCULATED—————

Quarterly → annual aggregation — 2026

Flows are summed over four quarters; rates are recomputed from the annual totals, never averaged
Quarterly → annual aggregation — 2026
Item2026-Q12026-Q22026-Q32026-Q4Year (derived)
T-01Water produced (m³)—————
T-02Water sold (m³)—————
T-03Water-loss rate (%)—————
T-13Electricity consumption (kWh)—————
T-14Electricity unit use (W/m³ (as printed))—————
B-08Water-sales revenue (riel)—————
F-04Total revenue (riel)—————
B-03Customers at end of period (customers)—————
Variance = actual − plan; variance % = (actual − plan) ÷ plan × 100; plan rate = actual ÷ plan × 100 (provisional reading of អត្រាផែនការ). Operator plans are distinct from M11 KPI targets, which remain TBC.
GD-CWA-04 · GD-CWA-06 · GD-CWA-16